BIRKAPILI HEPP
On November 24, 2000, ERE Hydroelectric Co. (previously ERE Autoproducer Co.) and the Ministry of Energy and Natural Resources signed the Autoproducer contract for Birkapili HEPP
Upon enactment of Energy Market Law No:4628, it is decided to establish the project under free electricity market conditions and a Generation Licence for 40 years was issued by EMRA on June 5th, 2003.
Upon completion of works, Preliminary Acceptance is signed on March 11th 2004 and Commercial Operation commenced.
The project, located in Icel Province in southern Turkiye, is expected to generate 177.6 GWh of electricity annually, with an installed power of 48.5 MW
Birkapili HEPP’s 1,010m Nominal Head is the highest in Turkey and also among world rankings.


Birkapılı HES Cebri Borusu
First of the two primary schools being built by ERE in the project site, ERE – Dagpazari Primary School opened with the ceremony held on September 22nd, 2003. Our second school, ERE – Yapinti Primary School is also completed and opened for education on 2004-2005 semester.
Detailed information regarding the project is available at the following links;
BIRKAPILI HEPP Opening Ceremony, April 30th, 2004
Works of ‘Sogutozu & Dagpazari Regulators and Birkapili HEPP’ which had commenced on October-2001 were completed on March-2004 and plant had started commercial opertion, following the Preliminary Acceptance on March 11th, 2004.
Opening Ceremony of the plant is held on April 30th, 2004, with the kind participations of Minister of Energy Dr. Hilmi GULER, Energy Market Regulatory Authority Chairman Mr. Yusuf GUNAY and Mr. Korkut OZAL alongwith a strong interest from protocol, local public and guests.
We would like to present our sincere gratitude to all our guests who honoured our ceremony with their attendance.
Photographs from the Opening Ceremony

Birkapılı HEPP Opening Ceremony

Members of the Protocol, during ceremony (from right to left);
· Dr. Hilmi GULER, Minister of Energy
· Mr. Yusuf GUNAY, Chairman of Energy Market Regulatory Authority
· Mr. Korkut OZAL
· Mr. Resat KOYMEN, Chairman of ERE Holding

Minister of Energy Dr. Hilmi GULER delivering his speech

ERE Holding Chairman Mr. Resat KOYMEN delivering his speech

ERE Holding Chairman Mr. Resat KOYMEN presenting a commemorative plaque to Minister of Energy Dr. Hilmi GULER

(from right to left) Chairman of Energy Market Regulatory Authority Mr. Yusuf GUNAY - Minister of Energy Dr. Hilmi GULER - Korkut OZAL during the ribon-cutting ceremony for opening of the plant

Birkapili HEPP, inside the plant

Penstock - General View

Headpond

Penstock - Manhole Works

Powerhouse and Switchyard

Generator - Stator and Piling/Winding Completed

Generator - Rotor In Assembly Pedestal, Poles Assembled

Generator - Rotor Lifted

Generator - Rotor Placing Into Stator

Generator - Rotor Placing Into Stator, Upwards View From Turbine Pit

Generator - Rotor In Place

Generator - Placing Upper Bracket

Generator - Cooling Water Piping

Powerhouse - Generator Bus-Duct and LV System Cubicles

Powerhouse - LV System Cubicles, Cooling Water Piping and Cabling

Powerhouse - LV System Cubicles and Cooling Water Piping

Turbine - Pelton Runner
| DAGPAZARI REGULATORS and BIRKAPILI HEPP GENERAL TECHNICAL INFORMATION |
|
|---|---|
| Project Location | Mut Province
– ICEL |
| REGULATOR I | |
| Height Above
Foundation |
3.10 m |
| Normal Water Level | 1,434.50 m |
| Crest Length | 7.50 m |
| Regulator Type | Front Intake,
Concrete Mass |
| REGULATOR II | |
| Height Above
Foundation |
6.00 m |
| Normal Water Level | 1,229.00 m |
| Crest Length | 35.00 m |
| Regulator Type | Front Intake
– with Spillway |
| POWER TUNNEL (1&2) | |
| Type | Basket Handle |
| Slope | 0.0006 |
| Length (1) | 3,195.00 m |
| Length (2) | 3,092.00 m |
| OPEN CHANNEL (1&2) | |
| Type | Rectangular reinforced concrete |
| Slope | 0.0003 |
| Length (1) | 138.00 m |
| Length (2) | 1 ,875.00 m |
| HEAD POND | |
| Width | 27.00 m |
| Length | 50.00 m |
| Volume | 8,100.00 m3 |
| PENSTOCK | |
| Type | Welded Steel |
| Diameter | 1.35 – 1.10 m |
| Length | 3,482.69 m |
| Thickness | 10 – 28 mm |
| POWER HOUSE | |
| Width | 19.90 m |
| Length | 21.10 m |
| Height | 28.20 m |
| TURBINE | |
| Type | Vertical
Axis Pelton |
| Design Flow | 6.18 m3/s |
| Design Head | 1,010.00 m |
| Unit Power | 48.50 MW |
| No of Units | 1 ad. |
| Installed Power | 48.50 MW |
| GENERATOR | |
| Type | Vertical
Axis Pelton |
| Unit Power | 53.44 MW |
| No of Units | 1 ad. |
| Installed Power | 53.44 MW |
| Current | 11.0 + 2.5%kV |
| Efficiency | 0.97 |
| AVERAGE ANNUAL POWER PRODUCTION |
177,600,000 kWh |
ERE - Yapinti Primary School Photos

Sports Hall - locker rooms and admin units

Sports Hall - interior

Sports Hall - exterior

Computer Class

New School

(left-to-right) Existing School - New School - Sports Hall

Existing School
DAGPAZARI Project, November - December 2003

Penstock General Layout

Sogutozu Weir

Dagpazari Weir

Settling Basin, Maiden Filling

Pelton Turbine, 5 Injectors and Runner Pit

Generator Erection

Cooling Water System, Piping Works

Generator Bus-Duct and AC-DC & Auxiliary System Cubicles

Control Room, Control Cubicles

Switchyard and Powerhouse, General Layout

Generator Rotor Transportation (60 tonnes)

Unloading the Rotor at Powerhouse

Rotor (poles not installed yet)

Lifting the Rotor

Rotor Lifted

Rotor in Erection Pedestal
DAGPAZARI Project, October 2003

Sogutozu Regulator - weir construction

Sogutozu Regulator - completed weir and reservoir

Powerhouse - transformer and loading channel

Santral Binası - şalt sahası montaj işleri

Powerhouse - switchyard erection works

Powerhouse - generator piling

Powerhouse - generator piling

Powerhouse - control room and operation panels
ERE - Dagpazari Primary School Ceremony

ERE – Dagpazari Primary School, Inaguration Ceremony

ERE Holding Chairman H.Resat KOYMEN adressing the guests and students

ERE Holding Chairman H.Resat KOYMEN and ERE Hidroelektrik Co. Chairman N.Nadi BAKIR presenting a memorial plaque to A.Atilla OSMANCELEBIOGLU, Governor of Mersin

Protocol Guests of the Ceremony (L-R)
· Garrison Commander, Brigader Admiral Abdullah AKGUL
· Governor of Mersin, A.Atilla OSMANCELEBIOGLU
· Mersin PM, Ali ER
· Mersin PM, Saffet BENLI
· Head Official (sub-Governor) of Mut, Harun KAYA
· General Director of Primary Education at Ministry of Education, Huseyin CALIK
· ERE Holding Chairman, H.Resat KOYMEN
· Mayor of Mut, Selahattin ASLAN
· ERE Hidroelektrik Co. Member of Board, Erdal CEYHAN

Computer class furnished by ERE Holding

A classroom from ERE – Dagpazari Primary School

Inaguration ceremony of ERE – Dagpazari Primary School

ERE Holding Chairman H.Resat KOYMEN, Governor of Mersin A.Atilla OSMANCELEBIOGLU and Garisson Commander Birg.Adm. Abdullah AKGUL during ribbon-cutting ceremony

ERE Holding managers and colleagues, teachers and students together after the ceremony

ERE Holding Chairman H.Resat KOYMEN and General Director of Primary Education at Ministry of Education Huseyin CALIK with the students.
DAGPAZARI Project, September 2003

Dagpazari Weir, completed

Penstock, anchor block 2nd phase concrete

Penstock, erection works

Penstock, erection trolley

Powerhouse, PLC & Control Room, end of Penstock

Turbine, Upper Housing erection

Generator, Lower Bracket erection

Generator, 3rd stage concrete

Generator, pit and anchors ready for Stator erection

LV system, 400V panels
DAGPAZARI Project, August 2003

ERE-Dagpazari Primary School - will open for education on 2003-2004 semester

Headpond - Power intake structure, concreting works

Penstock - Erection trolley and ground crane

Powerhouse - general view and Generator Lower Bracket

Turbine - Pit Liner erection

Turbine - Upper Housing welding

Turbine - Pit Liner and Distributor

Turbine - Inside the Pit Liner and Injector nozzle

Turbine - Pit Liner and Distributor, rebars for 2nd phase concrete

Penstock - Foundation concreting of SM35-Powerhouse section
DAGPAZARI Project, July 2003

Powerhouse Construction (01/07/2003) - final concreting works

Powerhouse Construction (19/07/2003) - roof erection

Powerhouse Construction (20/07/2003) - roof erection

Powerhouse Construction (19/07/2003) - roof completed, transformer unloading

Powerhouse - overhead crane erection

Powerhouse - roof erection

Powerhouse - overhead crane and roof completed

Powerhouse - view of generator floor

Turbine Erection - inspection platform and beams

Penstock - concrete platform and erection trolley rails for section AB16-AB20

Penstock - erection trolley for section AB16-AB20

Penstock - excavation of route btw. AB35-Powerhouse

Main Transformer (74 tons) - transportation
DAGPAZARI Project, June 2003

Powerhouse Construction (26.05.2003), view from down-stream

Powerhouse Construction (26.05.2003), view from AB36 at penstock route

Powerhouse - generator pit (completed) and wall concreting

Powerhouse - view upwards from turbine pit

Powerhouse - generator and turbine pit

Powerhouse - inlet valve and turbine hall

Penstock - concreting of AB20

Penstock - pipe weld, sliding support and expansion joint

Penstock - view downwards from AB4
DAGPAZARI Project, May 2003

Dagpazari Diversion Weir (regulator); installation of radial gate

T1 Tunnel; concreting of side-walls

Headpond (water intake structure not yet completed) and start of Penstock

Penstock; sliding support and 'ring girder' installation

Penstock; upstream view from Anchor Block No:8

Powerhouse Construction (10.05.2003)

Powerhouse Construction (21.05.2003)

Powerhouse Construction (29.05.2003)
DAGPAZARI Project, March-April 2003

T2 Tunnel (3,232.84m in total) was completed when excavation from Head:1 (1,517.96m) and Head:2 (1,714.88m) met on 29.03.2002, at 23:50 hours. (mini-loader working on debris of final explosion)

Settling Basin (entrance transition and gate housings completed)

Penstock Transportation (first shipment from IPC Co., Hungary)

Penstock, Unloading at Site

Penstock Erection

Powerhouse Construction (11/03/'03)

Powerhouse Construction (29/03/'03)

Powerhouse Construction (17/04/'03)
DAGPAZARI Project, January-February 2003

Settling Basin (entrance and exit transitions not yet completed)

Power House Excavation

Power House Excavation (completed)

Power House Construction (26/02/'03)

Penstock Fabrication (IPC Co., Hungary)

Penstock, Post-NDT Measuring-Sandblasting-Painting
DAGPAZARI Project, December 2002

Penstock and Power House Excavation

Settling Pond Interior

Settling Pond Entrance (view from T1 exit)

View of Settling Pond From Inside T2

T2 Tunnel (3,140.71m in total) was completed when excavation from Head:3 (1,365.14m) and Head:4 (1,775.57m) met on 21.12.2002, at 07:30 hours.

Site Team and Management Staff at the Meeting Point of Simultaneous Excavations (from Entrance:3 and Entrance:4) of T2 Tunnel
DAGPAZARI Project, November 2002

Sogutozu Regulator

Sogutozu Regulator

Dagpazari Regulator

Tunneling Works

Settling Pond

Penstock Route Excavation
DAGPAZARI Project, September 2002

Sogutozu Transmission Channel

Dagpazari Regulator and T1 Entrance

Head Pond

Head Pond

Penstock Route Excavation

ERE Primary School
DAGPAZARI Project, July 2002

Open channel concreting

T1 entrance

Headpond

Sogutozu gallery exit

Sogutozu gallery exit

Sogutozu gallery entrance and transmission channel excavation
DAGPAZARI Project, Dec'01 - Jun'02

Open channel - completed section (May 2002)

Open channel - concrete walls (April 2002)

Tunelling works (April 2002)

T1 exit (April 2002)

T2 exit (April 2002)

Open channel - bottom slab (March 2002)

Tunnel lining (steel supports + shotcrete) (March 2002)

Open channel - T2 exit (March 2002)

T2 entrance (March 2002)

T1 entrance (March 2002)

T2 exit (February 2002)

T1 exit and acces road excavation (February 2002)

T1 exit (December 2001)

T1-T2 channel - excavation (December 2001)